MINERAL PROCESSING KNOWLEDGE · TESTING AND FLOWSHEET DEVELOPMENT
A practical checklist of ore, testwork, capacity, product, water, power and site information needed before comparing mineral processing equipment and flowsheets.
Technical overview. Actual process selection depends on representative ore samples, mineralogy, testwork and site conditions.
Selecting equipment for a mineral processing plant should begin with the ore, not with a machine catalogue. Two deposits described by the same commodity name can behave differently because their mineralogy, texture, hardness, particle-size distribution and gangue associations are different. A reliable preliminary equipment list therefore starts with a clear project brief and representative technical information.
Technical note: This article is a project-preparation guide, not a plant design or a performance guarantee. Final equipment sizing, flowsheet selection and recovery estimates require representative sampling, suitable laboratory or pilot testwork, engineering review and site-specific design.
1. Identify the ore and the project objective
Begin with the commodity and the actual mineral or material to be processed. “Gold ore”, “iron ore” or “silica sand” is not enough to select a flowsheet. Record the deposit type, known valuable minerals, major gangue minerals and any important variability between mining zones or stockpiles.
- Commodity and ore type (for example, magnetite, hematite, sulfide copper, oxide copper, alluvial gold or hard-rock gold).
- Known valuable minerals and their approximate proportions, where available.
- Main gangue minerals and deleterious components such as silica, alumina, sulfur, phosphorus, clay or organic material.
- Whether the material is fresh, weathered, oxidized, altered, clay-rich or blended from several sources.
- The desired final product: concentrate grade, product size, impurity limits, moisture target or another customer specification.
2. Provide representative assay and mineralogy data
A head assay gives the chemical composition of a sample, but chemistry alone does not show how minerals are connected or how readily they can be separated. Where the project is sufficiently advanced, provide assay results together with mineralogical information such as XRD, automated mineralogy, microscopy or diagnostic test results. The useful method depends on the ore and the question being answered.
- Head grade and the analytical method used.
- Assays for elements that may affect product quality or downstream processing.
- Mineral identification and estimated mineral proportions.
- Mineral associations, inclusions, coatings and intergrowths.
- Evidence of free or liberated valuable particles, if known.
- Variability samples from different zones, benches, depths or stockpiles.
3. Describe feed size, hardness and liberation
The plant must receive a defined feed envelope. State the maximum lump size, full size distribution where available, moisture and clay content. For hard-rock ores, provide any available hardness or comminution test results. The required grind size should be determined from liberation and separation testwork rather than copied from another plant.
| Information | Why it matters |
|---|---|
| Maximum feed size and size distribution | Defines crushing, screening, feeding and classification duties. |
| Ore hardness / comminution testwork | Helps compare crushing and grinding energy and equipment options. |
| Moisture and clay content | Affects screening, washing, handling, slurry preparation and water balance. |
| Liberation size and mineral texture | Helps set a testable grinding target and identify suitable separation methods. |
| Slimes and fines proportion | May affect gravity, magnetic separation, flotation and dewatering performance. |
4. Define capacity and operating schedule
Capacity must be expressed clearly. Distinguish tonnes per hour from tonnes per day, and distinguish instantaneous design feed from average operating throughput. State the planned operating hours per day, days per year, availability assumptions, expected feed variability and whether the plant will be fixed, modular or mobile.
- Target throughput in t/h or t/day.
- Operating hours per day and shifts.
- Expected annual operating days.
- Single-line or multiple-line preference.
- Future expansion target, if known.
- Availability of operators, maintenance support, spares and utilities.
5. Specify the product and recovery objectives
A process route is evaluated against a product specification and a mass balance, not against a machine name. State the required concentrate grade or product quality, target size range, moisture limit and any penalty elements. If a recovery target has been set by a buyer or downstream smelter, identify its basis and whether it is a contractual requirement, a study target or an early estimate.
Avoid treating a generic recovery percentage as a guarantee. Recovery depends on mineralogy, liberation, test conditions, process control, water chemistry, operating discipline and the definition of the measured product.
6. Explain water, power and site conditions
- Fresh-water availability, water quality, recycling requirements and seasonal constraints.
- Power supply, voltage, frequency and reliability.
- Site location, elevation, climate, rainfall and ambient temperature.
- Available footprint, foundations, access roads and lifting constraints.
- Tailings storage, filtration, water return and environmental requirements.
- Local permitting, chemical handling rules and occupational safety requirements.
7. Share testwork and existing plant information
If laboratory, pilot or operating data exist, provide the report rather than only its headline conclusion. Useful information includes sample origin and mass, preparation method, test conditions, size-by-size assays, mass balance, reagent conditions, water chemistry, repeatability and the limitations noted by the laboratory. For an existing plant, provide a flowsheet, equipment list, operating data and any known bottlenecks.
- Representative sampling report and sample chain of custody.
- Crushing, grinding, gravity, magnetic, flotation or leach test reports as relevant.
- Size-by-size assays and mass balances.
- Pilot plant observations, if available.
- Existing flowsheet, equipment drawings and operating records for brownfield projects.
8. A practical first-contact checklist
A buyer does not need to have every report ready before making an initial enquiry. The following minimum information is a useful starting point. Missing items can be identified and prioritized during the first technical discussion.
- Country and project location.
- Ore or material type and whether it is alluvial or hard rock, oxidized or sulfide, magnetite or hematite, where relevant.
- Target feed capacity in t/h or t/day.
- Approximate feed size and any known grade or assay.
- Desired product or concentrate specification.
- Available water and power conditions.
- Photos, videos, sample descriptions and existing test reports.
How LiCheng Tech can help
LiCheng Tech can use the information above to review relevant equipment options in its current product range and coordinate enquiries with suitable Chinese suppliers. The purpose of the initial review is to identify missing data, compare possible equipment duties and establish what further testwork or engineering is needed. A final flowsheet should be based on verified project information, not on a generic equipment list.
Explore the Mineral Processing Solutions, review the Gold Ore Processing and Iron Ore Beneficiation pages, or send your project information.